Owner:
Chicago Public Schools
1819 West Pershing Road
Chicago, IL 60609
Project:
Gately Stadium
810 East 103rd Street
Chicago, IL 60628
Construction Manager:
d'Escoto, Inc.
One East Erie, Suite 520
Chicago, IL 60611
Project Type:
Rehabilitation
Size: (Seating)
7,500
Dates of Vistara Involvement:
September 97 - June 1999
Estimated Construction Cost:
$1,150,000
Actual Construction Cost:
$1,150,000
 View of the New Astro Turf Surface
|
Contact Person:
Dr. J.W. Smith, Executive Director
773/535-7959
Contact Person:
David Masur, DLM Architecture
847/763-1416
Contact Person:
Mary Ann Urroz, Project Manager
312/787-0707

Metallic Bleachers with Strip Resistant Coating
Scope of Work:
This stadium was constructed in the mid 1950's and consists of metallic bleachers on the East and West sides. The astro-turf playing surface, parking lot, locker rooms, toilets and bleachers were either renovated or replaced.
Our work included identifying and estimating costs associated with repairs to all the above areas, in addition to electrical problems created by poor cabling and switchgear for the stadium lighting.
Vistara helped negotiate a mutually acceptable solution to provide accessibility to disabled patrons and students, with the Mayor's Office for People with Disabilities.
|